OIG on Undefinitized Contract Actions
11 March 2003: NASA OIG: NASA’S Reduction of Undefinitized Contract Actions, NASA OIG (link to full report)
“We found that NASA had significantly reduced both the number and dollar amount of UCAs since the General Accounting Office highlighted them as one reason for identifying contract management as a major management challenge for NASA. By November 30, 2002, NASA had reduced the number of UCAs to 19 with a total estimated value of $61 million, representing reductions of about 90 percent in the number of UCAs and 97 percent in estimated dollar value. We also found that three Centers reviewed had inconsistent policies, which could cause inaccurate UCA reporting on certain relatively low-value contracts.”