ET Update
Editor’s note: Results from today’s PRCB (chaired by John Shannon) include the following decisions: External Tank Processing will be done at Michoud. ET-119 will be off-loaded from the barge and ET-120 will be loaded aboard the barge. The Michoud NDE (Non Destructive Evaluation) team will be ready by 3 Oct. ET-120 will arrive at Michoud on 5 Oct. and NDE will start. The barge will return to KSC and pickup ET-119 and be back at Michoud around 20 October.