This is not a NASA Website. You might learn something. It's YOUR space agency. Get involved. Take it back. Make it work - for YOU.
Budget

GAO on NASA: Assessment of Selected Large-Scale Projects

By Keith Cowing
NASA Watch
March 3, 2011
Filed under ,

GAO Report: NASA: Assessment of Selected Large-Scale Projects
“GAO assessed 21 NASA projects with a combined life-cycle cost that exceeds $68 billion. Of those 21 projects, 16 had entered the implementation phase where cost and schedule baselines were established. Development costs for the 16 projects had an average growth of $94 million–or 14.6 percent–and schedules grew by an average of 8 months. The total increase in development costs for these projects was $1.5 billion. GAO found that 5 of the 16 projects were responsible for the overwhelming majority of this increase. The issue of cost growth is more significant than the 14.6 percent average would indicate because it does not capture the cost growth that occurred before several projects reported baselines in response to a statutory requirement in 2005.”

NASA Watch founder, Explorers Club Fellow, ex-NASA, Away Teams, Journalist, Space & Astrobiology, Lapsed climber.