GAO Notes Continued Delays In NASA Commercial Crew

NASA commercial Crew Program: Schedule Uncertainty Persists for Start of Operational Missions to the International Space

"As of May 2019, both contractors had delayed certification nine times, equating to more than 2 years from their original contracts (see figure). This includes several delays since GAO last reported in July 2018. ... NASA's ability to process certification data packages for its two contractors continues to create uncertainty about the timing of certification. The program has made progress conducting these reviews but much work remains. In addition, the program allowed both contractors to delay submitting evidence that they have met some requirements. This deferral has increased the amount of work remaining for the program prior to certification. In February 2019, NASA acknowledged that delays to certification could continue, and announced plans to extend U.S. access to the ISS through September 2020 by purchasing seats on the Russian Soyuz vehicle."

  • submit to reddit


Loading



Global MilSatCom, November 5-7, 2019, London, UK






Monthly Archives

About this Entry

This page contains a single entry by Keith Cowing published on June 20, 2019 11:54 AM.

Risk And Exploration Go Hand In Hand was the previous entry in this blog.

OMB Has Its Sights Set On Gateway is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.