This is not a NASA Website. You might learn something. It's YOUR space agency. Get involved. Take it back. Make it work - for YOU.
Commercialization

GAO Report On NASA: Things Cost More And Take Longer

By Keith Cowing
NASA Watch
April 29, 2020
Filed under ,
GAO Report On NASA: Things Cost More And Take Longer

GAO Report: NASA: Assessments of Major Projects, GAO
“The National Aeronautics and Space Administration’s (NASA) portfolio of major projects continued to experience significant cost and schedule growth this year and the performance is expected to worsen. Since GAO last reported on the portfolio in May 2019, cost growth was approximately 31 percent over project baselines–the third consecutive year that cost growth has worsened after a period of decline. The average launch delay was 12 months, compared to 13 months last year.
Additional cost growth and schedule delays are likely after NASA establishes a new launch date for Artemis I–an uncrewed test flight of the Space Launch System, Orion crew capsule, and associated ground systems. Further, in 2019, GAO found that the Space Launch System (SLS) and Orion programs have underreported cost growth. GAO recommended that SLS calculate cost growth based on costs that are currently included in the first mission and that the Orion program update its cost estimate to reflect the schedule agreed to in its baseline. Both recommendations still require action to address. Looking ahead, NASA will continue to face significant cost and schedule risks as it undertakes complex efforts to return to the moon under an aggressive time frame.”

Excerpts:
“In addition, Boeing officials indicated the [SLS] core stage is the largest liquid hydrogen fueled rocket stage ever built and the green run test will be the first time the stage is filled with liquid hydrogen. Contractor officials indicated that one of the top remaining technical risks to the green run test is that the core stage may develop leaks when it is filled. … According to program officials, Boeing underestimated both the complexity of [SLS] core stage engine section assembly and the time and manpower that would be needed to complete the core stage effort. As a result, the estimated stages development cost has increased by about $1.4 billion and the stages contract effort now exceeds the contract’s negotiated cost ceiling.”
“The [Orion] program has reported development cost growth of 5.6 percent; however, the program has not completed a cost estimate that supports its baseline schedule. … According to program officials–in addition to the ESM delays–the Orion prime contractor has been underperforming and is in the process of renegotiating the contract due to exceeding its period of performance.”

NASA Watch founder, Explorers Club Fellow, ex-NASA, Away Teams, Journalist, Space & Astrobiology, Lapsed climber.

3 responses to “GAO Report On NASA: Things Cost More And Take Longer”

  1. Zen Puck says:
    0
    0

    Hi Keith.
    The link on this story does not take me to the GAO Report. IT takes me to a letter re Travel ban thru MAy/JUne…..or am I missing something?

  2. BeanCounterFromDownUnder says:
    0
    0

    This can hardly come as any surprise, except maybe to those who have had their heads buried in the sand a la one of Keith’s excellent caption pics.
    But fwiw the program has provided lots of those high paying jobs Congress likes to see and in lots of States so voters get their money’s worth after a fashion.
    Cheers
    Neil