Endeavour Maintenance Slips

By Keith Cowing
NASA Watch
January 12, 2005

Editor’s note: According to NASA sources, tomorrow (13 Jan) the PRCB will be told that OV-105 (Endeavour) maintenance will not be completed in time to support the STS-117 launch. A schedule slip of approximately 4 months will be identified. KSC has adjusted its resources to support preparation of OV-103 (Discovery) and OV-104 (Atlantis) for flight and is going to go a 24/7 schedule to support the STS-114/STS-300 Rescue missions and STS-121.In addition, charts will be presented at the PRCB suggesting a waiver of the 3 year period between major maintenance overhauls for OV-104 so as to allow more flights to compensate for the lack of a flight-ready OV-105.