Orion Phase A Life-cycle Review Done on Incorrect Configuration

NASA OIG: More Stringent Entrance Criteria Needed for Project Life-Cycle Reviews (Orion Project)

"The Orion Project Office (Project Office) conducted a Phase A life-cycle review with a vehicle configuration (606 vehicle) that was not at the proper maturity level to proceed to Phase B. Specifically, a required engineering design analysis conducted prior to the life-cycle review disclosed that the vehicle configuration required a reduction in weight, power, and instrumentation. However, instead of delaying the Phase A life-cycle review until the correct vehicle configuration (607 vehicle) could be reviewed, the Project Office proceeded with a nonconforming vehicle. As a result, a significant portion of the vehicle configuration that eventually did proceed to Phase B did not receive the benefit of a Phase A life-cycle review, nor was it completely evaluated for compliance with requirements."

  • submit to reddit


Loading



Humans to Mars Summit 2019
Military Space Situational Awareness April 1 - April 2, 2019, London, UK
MilSatCom USA conference will return to Washington from the 26th – 27th June 2019
Space Access Conference 2019
Mission To Methonē by Les Johnson - Baen Books



Join our mailing list




Commercialization: Monthly Archives

Monthly Archives

About this Entry

This page contains a single entry by Keith Cowing published on November 1, 2008 3:25 PM.

Job Cuts Are Inevitable at KSC was the previous entry in this blog.

Early Ammonia Servicer Reentry is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.