This is not a NASA Website. You might learn something. It's YOUR space agency. Get involved. Take it back. Make it work - for YOU.
SLS and Orion
LATEST
Yet Another Report Says NASA Has No Idea What SLS Costs
Yet Another Report Says NASA Has No Idea What SLS Costs

Keith’s note: According to a GAO report issued today: Space Launch System: Cost Transparency Needed to Monitor Program Affordability“: “Because the original SLS version’s cost and schedule commitments, or baselines, were tied to the launch of Artemis I, ongoing production and other costs needed to sustain the program going forward are not monitored. Instead, NASA created a rolling 5-year estimate of production and operations costs to ensure that the costs fit within NASA’s overall budget. However, neither the estimate nor the annual budget request track costs by Artemis mission or for recurring production items. As a result, the 5-year estimate and the budget requests are poor measures of cost performance over time. In 2014, GAO recommended that NASA develop a cost baseline that captures production costs for the missions beyond Artemis I that fly SLS Block I. NASA intends to fly SLS Block I for Artemis II, planned for 2024, and Artemis III, planned for 2025. NASA partially concurred, but has not yet implemented this recommendation. A cost baseline would increase the transparency of ongoing costs associated with SLS production and provide necessary insights to monitor program affordability.” Here are More posts in the continuing saga of what SLS actually costs. As if NASA will ever actually know who much these things cost. Why start now?

(more…)
  • NASA Watch
  • September 7, 2023
Only NASA Could Make A Reusable Engine Expendable – And Cost More
Only NASA Could Make A Reusable Engine Expendable – And Cost More

Keith’s note: According to a new NASA OIG Report NASA’s Management of the Space Launch System Booster and Engine Contracts: the complexity of developing, updating, and integrating new systems along with heritage components proved to be much greater than anticipated, resulting in the completion of only 5 of 16 engines under the Adaptation contract and added scope and cost increases to the Boosters contract. Additionally, Marshall Space Flight Center procurement officials who oversee all four contracts are challenged by inadequate staff, their lack of experience, and limited opportunities to review contract documentation. Marshall procurement officials also encountered significant issues with the award of BPOC, the follow-on booster contract, which started as an undefinitized letter contract in which terms, specifications, and price were not agreed upon before performance began. We found NASA took 499 days to definitize the letter contract, which is far outside the 180-day federal guidance. As a result, we question $19.8 million in award fees it received for the 11 unfinished engines which were subsequently moved to the RS-25 Restart and Production contract and may now be eligible to receive additional award fees. Faced with continuing cost and schedule increases, NASA is undertaking efforts to make the SLS more affordable. Under the RS-25 Restart and Production contract, NASA and Aerojet Rocketdyne are projecting manufacturing cost savings of 30 percent per engine starting with production of the seventh of 24 new engines. However, those savings do not capture overhead and other costs, which we currently estimate at $2.3 billion. Moreover, NASA currently cannot track per-engine costs to assess whether they are meeting these projected saving targets.”

(more…)
  • NASA Watch
  • May 25, 2023
Earth’s Most Powerful Rocket Roars To Life
Earth’s Most Powerful Rocket Roars To Life

Keith’s note: SpaceX just conducted a full duration static test firing of 31 Raptor engines (1 shutdown, 1 was shut down) on Starship producing enough thrust to still reach orbit – the most powerful rocket humans have ever built or fired. Sorry SLS. Video below.

(more…)
  • NASA Watch
  • February 9, 2023
NASA Will Try The Artemis Launch Thing Once Again
NASA Will Try The Artemis Launch Thing Once Again

Keith’s note: According to NASA PAO: “NASA confirmed it remains on track for the launch of the Artemis I Moon mission during a two-hour launch window that opens at 1:04 a.m. EST on Wednesday, Nov. 16. The launch countdown will begin at 1:24 a.m. on Monday, Nov. 14.” More.

(more…)
  • NASA Watch
  • November 12, 2022
A Cheaper Way To Fly SLS? Sure. Just Send Money.
A Cheaper Way To Fly SLS? Sure. Just Send Money.

Keith’s note: You have to read this solicitation to believe it. To build SLS NASA used existing Shuttle hardware to save money and then went off and reinvented everything that was “off the shelf” – making reusable SSMEs disposable, putting pieces together in new ways on Powerpoint, etc. Then they spent years and wasted billions of dollars to put it all together and tried to make it work. It is still sitting on the ground. Now NASA says that DST – Deep Space Transport – aka BoeingNorthropGrumman is the only company that is qualified to operate it. Well, DUH. NASA designed the whole SLS thing to be a one-off space system that no one in their right mind would build, much less want to operate. Can anyone operate it more cheaply? Of course not. Who’d even want to try? Just send money.

(more…)
  • NASA Watch
  • October 17, 2022
NASA's Latest Launch Date Guesses For SLS

Years late, billions over budget, and after multiple paint jobs, #NASA says that the latest notional 2022 launch dates for #Artemis 1 are 29 Aug, 2 Sep, and 5 Sep #CaveatEmptor pic.twitter.com/R7AzJM3DTc — NASA Watch (@NASAWatch) July 20, 2022

  • NASA Watch
  • July 20, 2022
OIG: NASA Is Not In Compliance With The Payment Integrity Information Act
OIG: NASA Is Not In Compliance With The Payment Integrity Information Act

NASA GAO Report: NASA’s Compliance with the Payment Integrity Information Act for Fiscal Year 2021 “We found that NASA was not in compliance with PIIA for FY 2021 because it did not publish improper payment estimates for the Space Launch Sy stem (SLS) program in the accompanying materials to the AFR as required by the statute. In our FY 2019 improper payment compliance audit, we reported that NASA failed to […]

  • NASA Watch
  • June 28, 2022
SLS Wet Dress Completed – Sort Of

Keith’s note: With the exception of an unresolved Hydrogen leak NASA told computers to ignore, it seems that the countdown to T-29 sec otherwise went as planned. The original plan was to bring it down to T-9.3 sec but was halted when a flag was encountered – so the test was not 100% completed. But NASA will try and spin it as if it was. So apparently the only way […]

  • NASA Watch
  • June 20, 2022
NASA Is Rolling SLS Back To The Barn For Repairs
NASA Is Rolling SLS Back To The Barn For Repairs

NASA to Discuss Status of Artemis I Moon Mission “Due to upgrades required at an off-site supplier of gaseous nitrogen used for the test, NASA will take advantage of the opportunity to roll SLS and Orion back to the Vehicle Assembly Building to replace a faulty upper stage check valve and a small leak on the tail service mast umbilical. During that time, the agency also will review schedules and […]

  • NASA Watch
  • April 17, 2022
NASA Mega Moon Rocket Tanking Test Fails – Again
NASA Mega Moon Rocket Tanking Test Fails – Again

Artemis I WDR Update: Third Test Attempt Concluded, NASA “Teams concluded today’s wet dress rehearsal test at approximately 5:10 p.m. EDT after observing a liquid hydrogen (LH2) leak on the tail service mast umbilical, which is located at the base of the mobile launcher and connects to the rocket’s core stage. The leak was discovered during liquid hydrogen loading operations and prevented the team from completing the test. Before ending […]

  • NASA Watch
  • April 14, 2022
Once Upon A Time NASA Actually Answered Questions

Always available for training in transparency to the news media. Here I am staying late after a press conference to explain our problems in depth as long as the media had questions. pic.twitter.com/wejfN5sIyR — Wayne Hale (@waynehale) April 12, 2022

  • NASA Watch
  • April 12, 2022
Summary Of Today's SLS Media Briefing

When asked what tests will not be done @NASA says "We will be missing loading operations for the upper stage itself". Ah, so only half of the rocket – the part with the crew capsule on top – will not be fully tested before launch. No problem apparently at #NASA pic.twitter.com/becglWu9Jv — NASA Watch (@NASAWatch) April 11, 2022 "The whole point of wet press is to decrease risk" says the […]

  • NASA Watch
  • April 11, 2022
NASA Is Moving The Goal Posts (Yet Again) On SLS
NASA Is Moving The Goal Posts (Yet Again) On SLS

Artemis I Wet Dress Rehearsal Update “NASA is planning to proceed with a modified wet dress rehearsal, primarily focused on tanking the core stage, and minimal propellant operations on the interim cryogenic propulsion stage (ICPS) with the ground systems at Kennedy. Due to the changes in loading procedures required for the modified test, wet dress rehearsal testing is slated to resume with call to stations on Tuesday, April 12 and […]

  • NASA Watch
  • April 11, 2022
NASA Stops SLS Test Before It Happens (Again)
NASA Stops SLS Test Before It Happens (Again)

NASA to Discuss Final Test Status Today Before Artemis Moon Mission “NASA will hold a media teleconference at 4 p.m. EDT today on Tuesday, April 5, to provide another update on the final major test with the agency’s mega Moon rocket and Orion spacecraft at the launch pad ahead of the uncrewed Artemis I lunar mission. Audio of the teleconference will stream live on the agency’s website.” Artemis I Wet […]

  • NASA Watch
  • April 5, 2022
Artemis 1 SLS Rollout
Artemis 1 SLS Rollout

NASA’s Moon Rocket Keeps on Rolling to Launch Complex 39B “NASA’s Space Launch System (SLS) rocket, with the Orion capsule atop, slowly rolls out of the Vehicle Assembly Building at the agency’s Kennedy Space Center in Florida on March 17, 2022 on its journey to Launch Complex 39B.” Costly and years late, NASA’s SLS moon rocket rolls to the launchpad for the first time, Washington Post “Last week, NASA’s inspector […]

  • NASA Watch
  • March 17, 2022
Does *Anyone* Know What A SLS Launch Actually Costs?

Last week #NASA SLS manager John Honeycutt disagreed with the @NASAOIG $4 billion/launch estimate for @NASA_SLS If he says it is not $4b then he must know what the real cost is, right? otherwise how can he say it is not $4b? #AskNASA pic.twitter.com/mYyChQEVHc — NASA Watch (@NASAWatch) March 14, 2022

  • NASA Watch
  • March 14, 2022
NASA Still Has No Idea What A SLS Launch Will Cost
NASA Still Has No Idea What A SLS Launch Will Cost

NASA SLS manager John Honeycutt pushes back against audit, AL.com “I will certainly say that the SLS rocket is not going to come at a cost of $4 billion a shot,” Honeycutt told an SLS media briefing at the Marshall Space Flight Center in Huntsville.” Keith’s note: OK, so John Honeycutt, the NASA SLS manager, is certainly in a position to know what the real cost of a single launch […]

  • NASA Watch
  • March 6, 2022