More Cost Increases And Delays For Webb Space Telescope

Media Telecon on Status of James Webb Space Telescope, June 27th

"NASA will host a media teleconference at 1 p.m. EDT [17:00 UTC], Wednesday, June 27, to provide an update on the agency's James Webb Space Telescope and the findings of an external independent review board. Webb will be the world's premier infrared space observatory and the largest astronomical space science telescope ever built. Audio of the call will stream live on NASA's website [https://www.nasa.gov/live]."

NASA Completes Webb Telescope Review, Commits to Launch in Early 2021

"The Independent Review Board (IRB) established by NASA to assess progress on its James Webb Space Telescope has unanimously recommended that development on the world's premier science observatory should continue; NASA has established a new launch date for Webb of March 30, 2021. A report issued by the review board addresses a range of factors influencing Webb's schedule and performance, including the technical challenges and tasks remaining by primary contractor Northrop Grumman before launch."

"As a result of the delay, Webb's total lifecycle cost to support the March 202l launch date is estimated at $9.66 billion. The development cost estimate to support the new launch date is $8.8B (up from the $8B development cost estimate established in 2011). Along with the IRB's broad-view assessment, NASA also considered data from the project's Standing Review Board (SRB). Both review panels had concluded that a 2020 launch date would have been feasible before the recent acoustics test anomaly."

"Northrop Grumman Aerospace Systems (NGAS) should establish corrective actions in processes, training, personnel certification, individual accountability and a robust testing, analysis and inspection process. Agree. NGAS stood down operations and performed an independent set of reviews and rewrites of all propulsion procedures including feedback from the performers. Also, applied Integration & Test (I&T) procedure expertise to manufacturing operations. To further enhance robustness in I&T, NGAS will be incorporating cross program independent reviews of the table top and pre-task briefing processes."

NASA Announces Contract for Next-Generation Space Telescope Named after Space Pioneer (2002)

"The James Webb Space Telescope is scheduled for launch in 2010 aboard an expendable launch vehicle. NASA today selected TRW, Redondo Beach, Calif., to build a next-generation successor to the Hubble Space Telescope in honor of the man who led NASA in the early days of the fledgling aerospace agency. Under the terms of the contract valued at $824.8 million, TRW will design and fabricate the observatory's primary mirror and spacecraft. TRW also will be responsible for integrating the science instrument module into the spacecraft as well as performing the pre-flight testing and on-orbit checkout of the observatory."

- Webb Space Telescope May Bust Its Budget Cap Yet Again (Updated) (2018)
- Management Shake Up on Webb Space Telescope (2018)
- Yet Another Webb Problem Review Panel (2018)
- More Cost Overruns and Delays for Webb (2010)

  • submit to reddit


Loading







Join our mailing list




Monthly Archives

About this Entry

This page contains a single entry by Keith Cowing published on June 27, 2018 12:43 PM.

Is The Force With The Space Force? was the previous entry in this blog.

Where Oh Where Did All Of That Webb Money Go? is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.